MBC undertook the replacement of the chiller which is located to the top of the roof.
Initially a temporary cooling system was installed prior to the existing chiller being disconnected from the pipework.
This was then removed from the roof by a crane, an exclusions zone was put in place and along with banks man around the perimeter.
The original chiller was removed and a new chiller was craned up and all pipework was installed.