Value - £592k
Duration - 18 weeks
Description – The project consisted of fire life safety works to the ground floor, first floor & second floor of the A & D Blocks at campion school.
The works consisted of the Demolition of classroom to corridor walls & the reconstruction of these to a compliant fire compartmentation detail to form protection corridors & lobbies.
In addition to this MBC Building contractors provided & certified new FD60 & FD30 doors throughout the protected areas. Undertook new ceiling installations with new lighting, fire detection & emergency lighting systems also installed throughout. MBC also upgraded the fire signage sealed all service penetrations in accordance with approved passive fire protection details